The South Jakarta District Court yesterday handed down its decision in the proceedings brought by the Indonesian Forum for the Environment (WALHI) in relation to the Sidoarjo mud flow incident.

The participants in the Brantas PSC successfully defended all claims brought against them in the proceedings.

Santos Brantas Pty Ltd has an 18% non-operating interest in the Brantas PSC.

Any appeal by WALHI must be lodged within 14 days with the relevant High Court.